Purchase Order Response. The EDIFACT message by which a supplier acknowledges, modifies or rejects a received order.
Definition
The ORDRSP message, per UN/EDIFACT D.96A, lets a supplier "respond to an order received from a buyer, in part or in whole, line by line". Three business functions:
- Confirmation (BGM 231 + 4343 AP): everything is accepted as is.
- Confirmation with changes: reduced quantity, postponed date, item substitution — flagged line by line.
- Rejection (BGM 231 + 4343 RE): the order is not fulfilled.
Origin
ORDRSP appeared in early-1990s EDIFACT directories as the contractual acceptance of the order. Directory D.96A archives the specification dated 27 November 1995. Most GS1 EANCOM integrations make ORDRSP a mandatory step before any DESADV.
Example in context
The supplier confirms the order but flags a stockout on line 3 and proposes a substitute. See the full message page: ORDRSP D.96A.